2021-11

Official Commencement of Works···

Goodnews arrivedon 20November 2021from Kazakhstan: works are officially commenced atShalkiya Lead & Zinc Project contracted by Consortium of JCHX and CCECC.A grand ceremony was held in the morning···

22

2021-10

JCHX Attending 11th Astana Int···

The 11th Astana International Mining and Metallurgy Conference (AMM) was held in Nursultan, capital of Kazakhstan from October 21 to 22, with the attendance of several world-famous mining companies, s···

10

2021-12

Congratulations on New Record ···

On 11 September 2021, LA COMPAGNIE MINIERE DE KAMBOVE SAS (hereinafterreferred to as COMIKA S.A.S) extended sincere congratulationson the new record of monthly development of 185m/4097.26m³ in August ···

13

2021-09

A Visit by Chris, CEO of Kamoa···

In the morning of 1 September 2021, Chris, CEO of Kamoa Copper, together with other representatives paid a visit to Musonoi Project, under the accompany byMr. Jianzhong Zhang, Advisor to GMof Overseas···

17

2021-08

ECL System Renovation to Drill···

For the purpose of energy conservation and consumption reduction, Kinsey completed ECL system renovation works to five drilling jumbos by 11 Aug 2021.At present, totally five Boomer 282 drilling jumbo···

23

2021-09

Noise Reduction & Sound Insula···

The sinking rate for two shafts at Bor project respectively exceeded 100m per month in June and July, despite of limited blasting time and vigorous measures over noise control

23

2021-09

Drainage Completed at Dikulush···

On July 25, the floorof -830mL chamber was finallyexposed, indicatingthesuccessfulcompletion ofdrainage at openpit of Dikulushi Copper Mine, which laida solid foundation for production recovery.Dikulu···

23

2021-09

Precise Breakthrough Achieved ···

On July 23, a precise breakthrough was achieved with high quality,efficiency and zero accident, between -30mL airconnection (developed by Kinsey – subsidiary of JCHX Mining) and 1# shaft (developed by···

20

2021-07

Successful Completion of Pavem···

On 1 July 2021, pavement of light duty decline at Kamoya Project was completed successfully with total length of 1705 meters

20

2021-07

A Letter of Appreciation Recei···

On 18 June 2021, I received a mail from Mr. Peter Zhou of Ivanhoe Mines, including a letter of appreciation from Co-Chairman Mr. Robert Friedland and Mr. Yufeng Sun. I was overwhelmed with joy and exc···

JCHX Mining Management Co Ltd.

010-83203999 

Public account

金诚信JCHX

Contact

Fax:010-83203999-9752

E-mail:jchx@jchxmc.com

Address (Miyun Office Area) : No. 28, Shuiyuan West Road, Economic Development Zone, Miyun District, Beijing

Postcode:101500

Address (Fengtai Office Area) : Jinxin Building, Building 12, Nord Center III, Fengtai District, Beijing

Postcode:100070

Copyright © 2018-2022 Jinxin Mining Management Co., LTD. All Rights Reserved

Record number: Beijing ICP No. 08105072