On February 1, a strategic cooperation agreement was signed between JCHX and Chanhen Group (“Chanhen”in short) in Chengdu. In the light of similar development goals, both parties have agreed to establ···

20

2021-01

The Chambishi Project Overfulf···

On January 5,2021,the Owner, NFC Africa Mining PLC,of the Chambishi Project senta congratulatory letter to JCHX and highly praised the Project for successfully overfulfilling 2020safety production tar···

20

2021-01

Monthly Advancing of the Kamoa···

In December, the Kamoa Project of Jimond Mining successfully fulfilled its 2020 yearly target with its monthly advancinghitting the record high for the year: 1510mof advancing, accountingfor 122% of t···

20

2021-01

A Cooperation Agreement Signed···

On January 15, 2021, the cooperation agreement of a copper mine project in the DRC was signed between JCHX and ERG during JCHX’s 2021 annual meeting.The signing ceremony was hosted by Dr. Peng Huaishe···

30

2020-12

Two Records Hitting Jinchuan P···

In the afternoon of November 25, the blasting of 97# drive of the 4th section at 1438mL marked the successful completion of production plan in November at Jinchuan Project, which was 5 days ahead of s···

30

2020-12

Contract Signed Between AMG Gr···

On November 18, the Design Contract of MUKULU Manganese Mine was signed between South Africa AMG Group and JCHX Design Institute Co., Ltd. in Beijing. As another large design project in South Africa f···

30

2020-12

Zijin Mining Serbia Congratula···

At 18:17 on November 17 (Serbian time), a successful breakthrough was achieved between air return shaft and decline at -80mL at Chukcalu-Paige Copper-Gold Mine, which was 3 days ahead of schedule. The···

30

2020-12

Successful Breakthrough at KAM···

On November 8, a successful breakthrough was achieved at north-south decline of KAMOA-KAKULA Copper Mine, which was 7 days ahead of schedule.Two main haulage tunnels extending from the south decline a···

30

2020-11

Metorex Congratulates JCHX on ···

On November 1, Metorex, the Owner of Musonoi Project, sent a warm congratulatoryletter to JCHX for the monthly excavatingand supportrecordof 133min Africa whichis achieved by Musonoi Project in Octobe···

30

2020-11

Drilling Commenced at Dikulush···

On November 3, drilling was successfully commenced at ZK0302 borehole at Dikulushi Silver & Copper Mine in DRC, JCHX’s first overseas resources project. The successfuldrilling marks the beginning ···

JCHX Mining Management Co Ltd.

010-83203999 

Public account

金诚信JCHX

Contact

Fax:010-83203999-9752

E-mail:jchx@jchxmc.com

Address (Miyun Office Area) : No. 28, Shuiyuan West Road, Economic Development Zone, Miyun District, Beijing

Postcode:101500

Address (Fengtai Office Area) : Jinxin Building, Building 12, Nord Center III, Fengtai District, Beijing

Postcode:100070

Copyright © 2018-2022 Jinxin Mining Management Co., LTD. All Rights Reserved

Record number: Beijing ICP No. 08105072